
TEMPO.CO, Jakarta - Electricity company PT PLN (Persero) stated that the major blackout in Sumatra on Friday, May 22, 2026, starting at 18:44 WIB (Western Indonesian Time), was caused by bad weather, which subsequently affected part of Sumatra's electrical system.
"Disruptions in the transmission lines had a widespread impact on part of Sumatra's transmission system, resulting in a frequency drop due to heavy generator loads and triggering a domino effect in several areas," said PLN's President Director, Darmawan Prasodjo, in an official statement on Saturday, May 23, 2026, as quoted by Antara.
According to Darmawan, as soon as the disruption occurred, PLN began inspecting and restoring the electrical system. He explained that the disrupted transmission network was successfully restored within about two hours.
Following the successful restoration of the transmission network, Darmawan said that PLN's main focus was to recommission generators that had previously been affected and realign them with the prepared transmission system.
He explained that the commissioning process for generators was carried out systematically and gradually, with a priority on system safety. Hydro and gas-based generators could immediately assist in supplying the system as a rapid response to hasten the initial recovery.
"Meanwhile, thermal generators such as coal-fired power plants require a longer time, between 15 and 20 hours from start-up, synchronization, and full operation," he said.
The recovery was carried out simultaneously from the transmission and substations to the generators in Sumatra's electrical system. To support this process, PLN deployed hundreds of personnel working 24 hours in various affected areas, including Jambi, West Sumatra, Riau, North Sumatra, and Aceh.
Read: PLN Restores West Sumatra Substation Following Blackout
Click here to get the latest news updates from Tempo on Google News
PLN Restores West Sumatra Substation Following Blackout
5 jam lalu

Local PLN ensures the swift restoration of the electricity system to return to normal as soon as possible.
Major Blackout Hits Parts of Sumatra, Indonesia
15 jam lalu

Major blackouts are reported in some areas of Aceh, North Sumatra, Riau, and West Sumatra on Friday night.
Solar Power Megaproject for Village Cooperatives
3 hari lalu

Government officials are scrambling to realize President Prabowo's ambitious 100-gigawatt solar power plant project.
How to Track Electricity Consumption and Cost
7 hari lalu

Changes in the amount of the electricity bill are caused by changes in consumption patterns or the addition of other cost components.
PLN Indonesia Power Eyes 495 MW Solar Plant Project in Bangladesh
7 hari lalu

This collaboration is part of PLN Indonesia Power's strategy to strengthen its position in the global market, particularly in the renewable energy sector.
116,000 Customers Benefit from Indonesia's Power Increase Discount Program
15 hari lalu

Increasing electricity power from 900 Volt-Ampere (VA) to 1,300 VA becomes the most chosen option for customers during the program.
Indonesia's Largest Industrial Solar Power Plant Inaugurated
23 hari lalu

The installation of this solar power plant comprises 36,862 solar panel modules spanning 122,783 square meters, approximately 12.2 hectares.
Danantara to Begin Rail Electrification Project in May 2026
24 hari lalu

Director of Operations at Danantara announced the plan to start the railway electrification project on May 20, 2026, aiming to improve efficiency, reliability, and support the 2060 Net Zero Emission target.
PLN Fully Restores Electricity in Jakarta After Outage
29 hari lalu

Most affected customers had their electricity supply restored by 12:23 PM local time, while the remaining 5 percent were reconnected by 03:05 PM.
Jakarta Suffers Second Blackout in a Month, Here's Why
30 hari lalu

Social media has been flooded with complaints of power outages in parts of Jakarta today. PLN blames power supply disruptions.
















































